# Army Corps weighs contracting route for Marine Corps microgrids in Japan

The planned projects aim to sustain operations without commercial grid power for at least 14 days; a proposed contracting model would bring a construction manager into design early.

Published 2026-11-24 by TGOs. Canonical: https://tgos.io/news/2026/11/24/army-corps-weighs-contracting-route-for-marine-corps-microgrids/

The U.S. Army Corps of Engineers' Japan District is seeking industry input on five Marine Corps microgrid projects in Japan.[1] The portfolio's total estimated acquisition value is $380 million to $600 million.[1] The Nov. 24, 2026, request for information is market research; no solicitation is available.[1]

The government anticipates using one or more Other Transaction agreements under 10 U.S.C. § 2808a with a Construction Manager at Risk model.[1] Under the proposed model, a construction manager would join during preconstruction to influence design alongside the architect-engineer firm, before negotiating the construction price.[1] It is also asking whether to use standard Federal Acquisition Regulation contracts.[1]

The portfolio covers MCAS Iwakuni, Camp Foster, Camp Hansen, Camp Courtney and Camp Fuji under the Energy Resilience and Conservation Investment Program.[1] The stated goal is islanded, cybersecure power supporting at least 14 days of continuous mission operations without the commercial grid.[1] Iwakuni's plan includes a 12,500 kW diesel plant, solar generation and battery storage.[1] The project aims to help maintain flightline and mission operations for Carrier Air Wing Five and Marine Aircraft Group 12.[1]

The notice distinguishes the proposed construction authority from prototype Other Transaction authorities, describing it as intended for military construction involving testing and experimentation with new and emergent construction technologies.[1] Industry responses are due Dec. 17, 2026.[1] The deadline is 14:00 Japan Standard Time.[1]

## Why it matters

Under the proposed model, the government would exercise construction execution if the guaranteed maximum price is accepted.[1] The awardee would propose that price at an agreed level of design, such as 95 to 100 percent.[1] If the parties cannot agree, the government retains the right to remove the contractor and complete the facility by alternative methods.[1]

## Sources

1. USACE Japan District market intelligence notice W912HV27ZOTA1, SAM.gov <https://sam.gov/api/prod/opps/v2/opportunities/ba493d6aa0d14ac290c14031e8ddeff0>