Contracts · Hypersonic strike
Navy seeks shipyards able to install USS Michael Monsoor’s hypersonic launcher
Installing the roughly 600-ton launch module requires heavy-lift capacity and coordination with government labs and weapon system prime contractors. The Navy plans a December industry day to discuss the modernization.

The Navy is assessing which shipyards can install the Large Missile Vertical Launch System (LMVLS) aboard USS Michael Monsoor for its Conventional Prompt Strike hypersonic weapon capability.1–2 A request for information (RFI) posted Nov. 17, 2026, seeks details on the engineering and infrastructure needed for the work.1
The Government plans to deliver the LMVLS as Government-Furnished Material
USS Michael Monsoor (DDG 1001)
The Government plans to deliver the LMVLS as Government-Furnished Material (GFM) as a fully out-fitted, pre-manufactured modular block.
The industrial effort will require rigging, lifting, transferring, lowering, and setting the ~600-ton LMVLS module into the hull pocket within tight spatial and angular tolerances.
A solicitation has not been prepared at this time.
Source: Naval Sea Systems Command notices, SAM.gov. As of Nov. 18, 2026.
The government plans to furnish a pre-manufactured module weighing roughly 600 tons, which a yard would lift into forward hull space reclaimed by removing the Advanced Gun System.1, 3 The RFI asks respondents to describe their crane capacity and how they would coordinate concurrent work with government labs and weapon system prime contractors. RFI responses are due Dec. 15 at noon Eastern.1
The Zumwalt-class program office, PMS 500, plans a technical-exchange industry day in Washington on Dec. 9. Attendance requires a formal response to the earlier sources-sought notice. Companies that have not responded have until Dec. 4 to do so.2
The office seeks industry-day attendance from companies holding a current PAE Maritime Master Ship Repair Agreement. Companies without one may participate if they intend to have an agreement before the modernization period is awarded and executed.2
The November industry-day notice lists the modernization period as May 2028 to August 2030.2 The April sources-sought notice anticipated four phased increments. Each would last five to eight months. The effort would span approximately mid-FY27 through mid-FY31.3
The market research could shape the competition: the April notice said responses would inform whether the requirement is set aside for small business or procured through full and open competition.3 The November industry-day notice says no solicitation has been prepared.2