Contracts · Aircraft survivability
Navy seeks suppliers for estimated $104 million countermeasures production contract
The planned AN/ALE-47 Common Carriage contract would move the system into rate production. Responses are due Oct. 30; the notice does not commit the government to an award.
The Naval Air Systems Command (NAVAIR) is seeking manufacturers to move the AN/ALE-47 Common Carriage countermeasures dispensing system from engineering and manufacturing development into rate production. Its Oct. 16 notice does not obligate the government to award a contract.1
Navy plans AN/ALE-47 Common Carriage rate production
Proposed Navy and Marine Corps contract; requirements for FY2028 through FY2030
The notice does not obligate the government to award a contract.
Source: NAVAIR, SAM.gov sources-sought notice. As of Oct. 16, 2026.
The modernization replaces the legacy round-magazine dispenser with a square-magazine design, increasing aircraft magazine capacity from 30 to 48 rounds. NAVAIR says the change aligns joint logistics with the Air Force, Army and F-35 platforms.1
NAVAIR estimates a $104 million contract across the Navy and Marine Corps. The planned ordering period would satisfy requirements for fiscal 2028 through 2030.1
NAVAIR anticipates a firm-fixed-price indefinite-delivery, indefinite-quantity contract and an award in May 2028. Initial production is estimated at 10 shipsets a month, with deliveries anticipated to begin as early as 12 months after each delivery order award.1
Required capabilities include producing thin-walled aluminum castings for the housing, machined blocks for the magazine and loading government-provided flight software onto the sequencer. Respondents must demonstrate certified quality controls such as AS9100.1
Capability statements are limited to 12 pages. Responses are due Oct. 30, 2026.1
Prospective suppliers must demonstrate they can manage and mitigate long-lead procurement of critical microelectronic components, with a supply chain structure that can support a 12-month post-award initial delivery schedule. They also need possession of or authorized access to the necessary technical data, or a viable plan to secure it.1